Wallpaper painting. Drawing up estimates for plastering works Painting wallpaper with water-based paint price in the estimate

(Examples are considered on the basis of TER-territorial unit prices, analogously and FER-federal unit prices,
according to the Reference Estimate and Regulatory Base (new edition))

Let's analyze example No. 5 of budgeting, this example will be more complicated:

For example, let's imagine that the Customer asks to repair the walls in the apartment.

We take a tape measure, a sheet of paper, a pen or pencil and leave to inspect the repair site, i.e. we go to the object.
Arriving at the site, we find out that the walls need to be repaired in only one room.
Here, on the spot at the representative of the Customer, we clarify what exactly the Customer wants.
The customer wants (only the walls are still considered without slopes):

1. Clean the walls from water-based paint;
2. Align the plaster walls;
3. Apply putty;
4. Paint the walls with water-based paint.

Ask the Customer for all the details, this will help you when choosing prices in the future.
After asking the Customer, we agreed that:

  1. We will first clean off the old paint from the walls;
  2. Prime the walls before leveling the plaster with a primer, to adhere a new layer of plaster to the old one (in other words, so that our plaster does not fall off);
  3. Align the plaster of the walls with a mixture of plaster "Rotband", the thickness of the plaster layer is up to 10 mm.
  4. Then prime the walls again with a primer, before applying putty and water-based paint, so that all this does not crack, fall off and adhere tightly to the wall.
  5. Apply putty on walls to even out wall defects after plastering;
  6. And the last thing, to paint the walls with water-based paint, the coloring was discussed with the Customer, it will be improved.
Stage II:

We figured out the problem, now we need to decide on the volumes. It is good if the Customer gives you a copy of the plan of the premises, which shows the dimensions of the premises being repaired. And if not, then we will give a tape measure and measure the width and length of the room, as well as the width and height of the door and window openings with a tape measure ourselves.
Let's say that when measuring the width of the room, we got 4.0 m, the length of the room is 6.0 m, the height of the room is 2.85 m. The height of the doorway is 2.0 m, the width is 1.0 m, the height of the window opening is 1.5 m , and the width is 1.4 m.
Be sure to measure the dimensions of the door and window openings in the room. When calculating the volume of walls, we will subtract the area of ​​the door and window openings from the total total area of ​​the walls of the room, since the amount of work to level the wall plaster is determined by the area of ​​only the surface that will be leveled. (GESNr 81-04-OP-2001 State elemental estimated norms for repair and construction works. General provisions. Calculation of the scope of work (2009 edition), para. 2.42. Plastering area internal walls should be determined minus the areas of openings along the outer contour of the boxes and the area occupied by the drawn platbands, and the height of the walls should be taken from the clean floor to the ceiling.)

But, the area for painting walls with water-based paint is determined without deducting the areas of openings and without taking into account the areas of window and door slopes only if we paint the slopes too. (GESNr 81-04-OP-2001 State elemental estimated norms for repair and construction work. General provisions. Calculation of the scope of work (edition 2009), p. 2.51. The area of ​​​​painting internal surfaces with water compositions is determined without deducting the areas of openings and without taking into account areas of window and door slopes, side surfaces of niches, but taking into account the areas of pillars and sides of pilasters.)

But since we do not paint the slopes, but only the walls, therefore, we take the area of ​​painting the walls with water-based paint specifically according to the area of ​​the surface to be painted.

Having mentally photographed the walls and measured them, we return to our place of work and proceed to the second stage.

We consider the area of ​​\u200b\u200bthe walls: (6.0 + 4.0) * 2 * 2.85-2.0 * 1.0-1.5 * 1.4 \u003d 52.9 m2.
Now we write in the defective statement what we need to do:

  1. Remove paint from wall surfaces by hand. We write to the defective statement - Manual cleaning of the surface of the walls from paints 52.9 m2.
  2. Prime the walls before leveling the plaster with a primer. We write to the defective statement - Priming the surface of the walls with a primer before leveling the plaster 52.9 m2.
  3. Align the wall plaster with a mixture of plaster "Rotband", the thickness of the plaster layer is up to 10 mm. We write to the defective statement - Leveling the plaster of the walls with a dry mortar mix "Rotband" up to 10 mm thick 52.9 m2.
  4. Prime the walls after leveling the plaster, before applying putty and water-based paint. We write to the defective statement - Priming the surface of the walls with a primer before applying putty and water-based paint 52.9 m2.
  5. Apply putty to the walls to even out defects after plastering. We write to the defective statement - Applying putty on the walls to level defects after plastering 52.9 m2.
  6. Paint the walls with water-based paint. We write to the defective statement - Improved painting with water-based compositions for wall plastering.
notice one important detail, all the details are written in the defective statement.

Specifically, in our case, we wrote not just "Leveling the plaster of the walls with a dry mortar mix" Rotband ""; "Improved painting with water-based emulsion compositions of the walls", and "Leveling the plaster of the walls with a dry mortar mixture" Rotband "thick up to 10 mm"; "Painting with water-based compositions on plaster improved walls" as requested by the Customer.
Why such details, you will understand later, when looking for prices.
Well, in our case, the defective statement is ready, see below:


"APPROVE"

________________ /______________________ /

"______" ____________________ 20___

Object: Apartment

DEFECTIVE STATEMENT

to repair the walls in the room

No. pp Name of works and costs unit of measurement Quantity
1 2 3 4
1. Manually cleaning the surface of the walls from paints m2 52,9
2. Priming the surface of the walls with a primer before leveling the plaster m2 52,9
3. Leveling wall plaster with dry mortar
"Rotband" up to 10 mm thick
m2 52,9
4. Priming the surface of the walls with a primer
before applying putty and water-based paint
m2 52,9
5. Applying putty on walls to even out defects after plastering m2 52,9
6. Improved water-based painting on wall plaster m2 52,9

Compiled by: _________________________________________________________
(position, signature, full name)

Checked by: _________________________________________________________
(position, signature, full name)


After the defective statement is ready, it is given to the Customer for approval.
And after the Customer approves the defective statement, we begin to draw up an estimate.

Drawing up a budget.
To draw up an estimate, we need TERr - Territorial unit prices for repair and construction work; TER-Territorial unit prices for construction work.
If you are already familiar with the estimate program, then all these TERr, TER are in it.
So we have a cleanup old paint, leveling the plaster, then painting with new paint, i.e. repair, so we are looking for prices first in the repair sections - TERr - Territorial unit prices for repair and construction work. And if there are no prices suitable for us in the repair sections, then we are looking for them in the construction parts.
But when repairing, prices are always initially searched for in the repair sections.
Initially, we manually clean the surface of the walls from paints. There is no direct quotation for this type of work, so we will look for a quotation applicable. Since the first type of work is related to paints, i.e. cleaning from paints, then we are initially looking for TERr-painting work. This will be TERr Section 62 Painting.
Moving on to TERr section 62. Painting work, we're looking for paint stripping. This will be the applicable rate TERr 62-41-1.
For the first item in the defective statement, we found a price - TERr 62-41-1. We put it in our budget.

Now we are looking for a price for the second item on the defective list.
The second type of work - priming the surface of the walls with a primer before leveling the plaster, we will not look for yet, since usually the priming is included in the prices for leveling the plaster.

We are immediately looking for the third type of work - leveling the plaster walls with a dry mortar mixture "Rotband" up to 10 mm thick.

Since the third type of work is related to plaster, i.e. leveling plaster, then we are looking for TERR-plaster work. This will be TERr Section 61 Plastering.
Further in TERr section 61. Plastering, we are looking for leveling plaster walls with dry mortar up to 10 mm thick. This will be the rate TERR 61-1-9.
We see that the price of TERr 61-1-9 is open, which means that the cost of the main material (in our case, this is the Rotband plaster mixture) must be taken in addition to this price according to TSTS, since in the price of TERr 61-1-9 he (the main material) is not taken into account. Therefore, in addition to the price of TERr 61-1-9, we additionally take the mixture of plaster "Rotband". The cost of materials is searched for in the TSTS collection. TSTS - a territorial collection of estimated prices for materials, products and structures used in construction. It consists of five parts:

  1. TSTS 2001 Part I. Materials for general construction works
  2. TSSC 2001 Part II. Building structures and products
  3. TSSC 2001 Part III. Materials and products for sanitary works
  4. TSSC 2001 Part IV. Concrete, reinforced concrete and ceramic products. Nonmetallic materials. Ready-mix concretes and mortars
  5. TSTS 2001 Part V. Materials, products and structures for installation and special construction work
Since the leveling of plaster is related to work with mortars, we are looking for a price for the cost of the Rotband plaster mixture according to TSTS 2001 Part IV. Concrete, reinforced concrete and ceramic products. Nonmetallic materials. Commodity concretes and mortars. This will be the price of TSTS 402-0077. In addition, we take the coefficient for the consumption of the material, the consumption of the Rotband plaster mixture according to TSTS 402-0077 will be 9.6 kg per 1 m2 with a layer thickness of 10 mm: 52.9 * 9.6 = 507.84 m2

For the second and third points in the defective statement, we found a price - TERr 61-1-9. We put it in our budget.

Next, we move on to the fourth and fifth types of work - priming the surface of the walls with a primer before applying putty and water-based paint and applying putty on the walls to level defects after plastering. We will not be looking for these types of work, just like the second one. Let us first consider the sixth type of work - Improved painting with water-based compositions for wall plastering, and then we will explain why we missed the fourth and fifth types of work.

Since there is no price in TERR for painting with water-based compositions for improved wall plastering, we turn to the construction parts of TER - Territorial Unit Prices for Construction Works.
We are looking for in TER - finishing work. This will be TER part 15. Finishing work. The rate that suits us is TER 15-04-005-03.
Consider this price TER 15-04-005-03 in more detail, an interesting price.

First of all, we need to find out whether priming and putty are included in the price of TER 15-04-005-03.
We look at GESN 81-02-Pr-2001 State elemental estimated norms for construction work. Annexes (edition 2009), Annex 15.11 - Scope of work when painting with polyvinyl acetate water-based compositions - improved for plaster. Here, in the table, we see that primer and putty are already included in the price for painting with water-based compositions for improved wall plastering. And therefore, we will not take separate prices for priming and putty before painting the walls with water-based paint.

At the rate of TER 15-04-005-03, you may have a question: "How is priming included in the price, if the price does not include the cost of this very primer according to TSSC?"

We explain that the paint consumption as part of the price TER 15-04-005-03 for improved painting is so high that part of this consumption can replace both the consumption of the primer and the cost of the primer itself. Therefore, it makes no sense to correct this price for the primer (see Letter of the Ministry of Regional Development of the Russian Federation dated July 21, 2009 No. 22729-IP / 08).

Now we can say that for the fourth, fifth and sixth items of the defective statement, we have found a suitable price - TER 15-04-005-03.

The estimate is almost ready, it remains to add all the necessary coefficients from the relevant MDS - Methodological documents in construction, such as, for example, according to clause 4.7. MDS 81-35.2004, if there are complicating factors and conditions for the production of these works, and reducing factors for overhead costs and estimated profit during repairs, this is also from MDS ( read more often and study MDS before making estimates) and you can release it.
The estimate will look like this, see

Just do not forget that the estimated prices in the collections and programs are based on the prices of 2000. Therefore, you must also multiply the final estimated cost in this estimate by the corresponding transfer index in current prices.
The index of conversion to current prices is different for each region.

After all that has been done, the finished estimate can be submitted for approval to the Contractor, and then for approval by the Customer.

AND NOW TRY TO SOLVE THE PROBLEMS OF BUDGETING AND CHECK YOURSELF IN THE SECTION:

Quote for wallpapering

Even for such a seemingly simple finishing work as wallpapering, there are estimates. The point is that one finishing work"pulls" others. Table 2 shows an example quotes for wallpapering in Saint Petersburg in 2014. Consider the performance of work on the example of a room.


The parameters of the room are indicated in table No. 1:

Table #1


* - the sum of the lengths of all sides of the room minus the doorway.


We remind you that...

Therefore, in order to compile wallpaper gluing quotes we need the area of ​​the walls.

FAQ


Do doors and windows count as part of the wall?

The area of ​​doors and windows does not count as part of the wall.

How to calculate the area of ​​\u200b\u200bthe walls yourself?

See article: how to calculate the area of ​​the walls of the room yourself ?

For people who find it difficult to independently calculate the area of ​​\u200b\u200bthe walls, you can use the formula:

Wall area = floor area * room height.

This formula allows you to roughly estimate the area of ​​\u200b\u200bthe walls in the room. The exact calculation is made by the master during the inspection.

So, in our room, the wall area is 55 m 2. For wallpapering, it is required not only to remove the old wallpaper, but also to remove the socket and switch frames, as well as to dismantle the old skirting boards. Removed plinths after wallpapering can be put back.

Let's look at the estimate (see table number 2):

Table number 2


Name of works unit of measurement Qty Unit price, rub. Cost, rub.
1. Preparatory work
1.1 removing old wallpaper sq.m. 55 50 2750
1.2 dismantling of skirting boards (with preservation) running meters 19,2 40 768
1.3 switch dismantling PCS. 1 50 50
1.4 dismantling of sockets PCS. 6 50 300
2. Main work
2.1 sticking non-woven wallpaper sq.m. 55 250 13750
3. Final work
3.1 installation of plastic skirting boards running meters 19,2 50 960
3.2 switch mounting PCS. 1 200 200
3.3 installation of sockets PCS. 6 200 1200
4. Optional
4.1 Delivery and removal of construction equipment to the site (ladders and tools) PCS. 1 1000 1000

Total: 20978 rubles.


The approximate cost of consumables is given in table No. 3:

Table #3


Total: 850 rubles.

What items are not included in the estimate?

Some work that may theoretically be needed is not included in the estimate. Let's see what kind of work it is.

1. Partial alignment of the walls

There are many options here. All rooms, like the walls in them, are different. Therefore the cost